Sempra Energy Subsidiary Port Arthur LNG Signs EPC Contract With Bechtel

Energy infrastructure company Sempra Energy (SE) and Bechtel said Tuesday that their respective subsidiaries, Port Arthur LNG, LLC as well as Bechtel Oil, Gas, and Chemicals, Inc., have signed a fixed-price engineering, procurement and construction or EPC contract for the Port Arthur LNG liquefaction project under development in Port Arthur, Texas.

As part of the EPC contract, Bechtel Oil, Gas, and Chemicals will perform the detailed engineering, procurement, construction, commissioning, startup, performance testing and operator training activities for the project, the companies said.

In addition, the scope of the agreement includes continuing pre-final investment decision engineering to better assure project cost and schedule certainty. Sempra Energy said that a final investment decision is expected in the third quarter of 2020.

The Port Arthur LNG development project is expected to initially include two liquefaction trains, two liquefied natural gas or LNG storage tanks, a marine berth and associated loading facilities as well as related infrastructure necessary to provide liquefaction services, with a nameplate capacity of about 13.5 million tonnes per annum (Mtpa) of LNG.

Sempra Energy noted that the project site sits on nearly 3,000 acres of land along three miles of the Sabine-Neches waterway and has the potential to become one of the largest LNG export projects in North America, with expansion capabilities of up to eight liquefaction trains and approximately 45 Mtpa of capacity.

The U.S. Department of Energy has authorized the Port Arthur LNG development project to export domestically produced LNG to countries that do not have a free trade agreement with the U.S. in May 2019. Additionally, the Federal Energy Regulatory Commission issued the approval to site, construct and operate the liquefaction-export facility in April 2019.

Sempra Energy said that the proposed project is expected to create a craft workforce on site that peaks at about 5,000 construction jobs, in addition to several hundred additional Texas jobs in support of the project, including material fabrication.

Nearly 200 long-term jobs will be created to operate and maintain the Port Arthur LNG facility, the company added.

For comments and feedback contact: editorial@rttnews.com

Business News

Editors Pick
Avalon Furniture is recalling about 9,500 units of Cottage Town Bedroom Furniture collection sold through Rooms To Go due to violation of federal lead paint ban, the U.S. Consumer Product Safety Commission said in a statement. According to the agency, the base coat paint used on pieces within the furniture collection contains levels of lead that exceed the federal lead paint standard. Sanofi and Regeneron Pharmaceuticals, Inc. announced that the U.S. Phase 3 trial of arthritis drug Kevzara (sarilumab) 400 mg in COVID-19 patients requiring mechanical ventilation did not meet its primary and key secondary endpoints. In the trial, Kevzara was added to best supportive care compared to best supportive care alone (placebo). The companies have stopped the U.S. trial. Shares of Moderna Inc. (MRNA) slipped over 5% on Thursday after a report claimed that the biotechnology company's late-stage trial for a coronavirus vaccine will be delayed. Moderna is developing mRNA-1273 in collaboration with the National Institute of Allergy and Infectious Diseases (NIAID). The...