Denison Mines Corp. (DNN,DML.TO) announced that, pending final regulatory approvals, it is prepared to make a final investment decision (FID) and begin construction of the proposed Phoenix In-Situ Recovery (ISR) uranium mine. Significant progress in regulatory, engineering, and construction planning throughout 2025 has positioned Phoenix in a construction-ready state, with confirmation of an expected two-year construction timeline. If approvals to commence construction are received in Q1 2026, first production remains on track for mid-2028.
The company has also provided an updated initial capital cost estimate for the Project, reflecting substantial completion of engineering and procurement activities since 2023.
Denison has prepared a Class 2 post-FID capital cost estimate to establish the Control Budget for the Phoenix Project. Roughly 75% of equipment and materials costs are already supported by committed contracts or bids under evaluation, while about 50% of construction costs are backed by bids currently being reviewed or finalized in contract negotiations.
Taking into account inflation, cost increases, and project refinements, the Company now estimates the total post-FID initial capital requirement for Phoenix at approximately $600 million, based on a Class 2 level of precision. This represents a 20% increase compared to the 2023 Phoenix Feasibility Study when adjusted for inflation. The updated estimate also includes $65 million in contingency funds and owners' reserves, equivalent to about 12.5% of the Project's direct and indirect costs.
For comments and feedback contact: editorial@rttnews.com
Business News
May 01, 2026 15:54 ET Central banks dominated the economics news flow this week with almost all major ones announcing their latest policy decisions and many boosted expectations for a rate hike in June. In other news, several countries released the preliminary data for first quarter economic growth. In the U.S., comments by Fed Chair Jerome Powell were also in focus as his term ends this month.